White Pine Shores
Monday, October 18, 2010
Finishing Touches
We are nearly trimmed out on both the Hubert Lake and Thistle Hill projects. Our focus is getting these homes finished inside before we tackle the siding and other miscellaneous jobs. Hopefully the nice weather continues when we do get outdoors!
Thursday, September 16, 2010
Lake Hubert Renovation
A new project started is an addition and renovation on Lake Hubert. The new wing includes a main entry, office, and sun room. The existing home will get a new face lift as well. New roof, windows, insulation, bathroom, laundry and flooring will give this family owned property a new chapter.
Monday, September 13, 2010
Where did summer go?
Summer has already pasts us by, hopefully we have a long fall in store. We have recently completed the Margret Lake addition which consisted of a theatre room with a large flat screen, custom surround sound, and custom theatre seating. Below, the basement was finished for a game room and outside we added on to the deck in order to connect with the game room.
Along with a few smaller projects, we have started a new home at the Thistle Hill British White Cattle farm. Three years ago, we built a small home on the property with the plan to someday add on and make it the customers permanent home. The new project will triple the size of the existing home.
Along with a few smaller projects, we have started a new home at the Thistle Hill British White Cattle farm. Three years ago, we built a small home on the property with the plan to someday add on and make it the customers permanent home. The new project will triple the size of the existing home.
Sunday, July 18, 2010
Happy Summer
We have come to the end of the project on Gull. It is bittersweet, it is always nice to come to the conclusion, but it was a lot of fun to work on this home. It has a lot of unique characteristics, like round cantilevered decks, spiral staircase with a fire pole, and a complete brick and stone exterior, all of which we will have pictures soon. We have also completed a cabin renovation on Gull and just started an addition to a home on Margret Lake, a home that we worked on recently.
Tuesday, May 25, 2010
Gull Lake Home
The new home on Gull Lake is near completion. All the trim on the interior is finished and the homeowners are settling in. The exterior is close. Two sides of the home are finished with stone and the other two sides are trimmed with stone but have brick covering the walls. The decks were finished with custom iron railings. We have also fit in a few other projects along the way that I will show soon. Happy memorial weekend!
Sunday, March 28, 2010
Gull Lake Home
Spring is here, and we are ready. It has warmed up enough to start the rock masonry work on the exterior of the house. On the inside, we are in full trim mode. The approximately 4000 sq ft of tile is set. Hickory doors, casing and base are being finished and the hickory cabinets are awaiting their granite tops.
Monday, February 1, 2010
Gull Lake Home
The house is now closed in and just in time for the coldest part of the year. All though there is still much work to do in the outdoors (soffit, decks, exterior wall coverings, etc.), there is a lot happening inside out of the cold. Framing fireplaces, framing whirl pool tub decks, drywall, tile, and lots more. All of the unique characteristics of this home are starting to take shape!
Subscribe to:
Posts (Atom)
Spirit Lake Cabin
Spirit Lake Cabin
Spirit Lake Cabin